In Quebec, Canada's newest hydroelectric dams nearly ready

November 21, 2018 by Clément Sabourin
A view of Hydro-Quebec's Romaine 1 dam floor in Canada—the huge construction project, ongoing for a decade, is nearing completion

On a frigid night, the roar of heavy machinery chipping away at rock echoes through Canada's boreal forest: in the far north of Quebec province, four massive hydroelectric dams that will produce "clean energy" for the northeastern United States are nearing completion.

Flowing more than 500 kilometers (300 miles) through the wilderness, the Romaine River in the Cote-Nord region of Quebec is about to hit a literal wall at 51 degrees north latitude with the erection of the fourth and last power station.

Once completed, the construction —which started in 2009—will see the cold, clear waters of one of Canada's longest untamed rivers flood surrounding lands claimed by indigenous tribes.

From a distance, the bright lights at the site where more than 800 heavy dump trucks, drills and giant backhoe loaders are in use look like reflections of stars in the night sky.

The teams from Hydro-Quebec are working on two fronts.

They are razing a mountain to make room for the power station. They are also erecting a dike 500 meters (1,640 feet) long and 90 meters high that will hold back the water to be used to generate electricity.

Quebec has a power surplus, so the government is hoping to sell the power produced here to its American neighbors to the south—and in turn do its bit to help alleviate global warming.

Hydro-Quebec plans to sell the clean energy generated by the Romaine project—the Romaine 4 dam is seen here—to customers in the northeastern United States
Dangers of dam building

The extends over several kilometers: there is a full cement factory, an infirmary for workers, offices, a quarry and a dynamite depot.

"This is a major project—there are many different stakeholders, many simultaneous activities, and many dangers to manage daily," including inquisitive wolves and bears, says Christian Guimond, who is in charge of the dam's construction.

Already four workers have died, which forced the public utility Hydro-Quebec to suspend construction in 2017 while it reviewed its workplace safety practices.

There's now a greater awareness of the risks for workers, said Guimond.

From atop a nearby mountain peak, he points to a kilometer-long tunnel and a ditch built to divert the raging river in order to start construction of the dam itself on the dry riverbed.

Two construction workers get ready to go up in a lift at the massive Hydro-Quebec construction site, which stretches over several kilometers

The dam is to be completed in 2019.

Costing more than Can$6.5 billion (US$4.9 billion), it is among the top 10 largest infrastructure projects currently underway in Canada, ranking behind two nuclear plant refurbishments, three other hydroelectric projects and a new Toronto subway line.

For residents of the region, the hydroelectric project has been a mixed blessing, creating jobs in a remote and economically-depressed region but flooding the local indigenous people's traditional hunting grounds.

"I didn't want it at first, but I needed work... when I got my first paycheck, I changed my mind about it," said Gilbert Pietacho, a foreman and member of the Innus of Mingan.

His father, who is also chief of the small tribe that lives on a reserve on the north shore of the Saint Lawrence River, is a fierce opponent of the project.

The chief has the backing of environmental groups, such as Greenpeace, which have decried huge hydroelectric dams as "ecologically devastating."

Gilbert Pietacho, a foreman at the dam construction site, is also a member of a local indigenous tribe—he says he was against the project at first, because it will flood traditional hunting grounds, but he is now on board
"It pains me, makes me sad what we're doing to nature," said Patricia Bacon, a 24-year-old Innu who came here to work at the cafeteria in order to pay for her university studies.

"But times have changed—every house must have electricity now."

Since the 1970s, hydroelectricity has supplied 90 percent of Quebec's power needs—the four new plants will generate enough electricity to power a city, or 1.5 million homes
Export to US

Once fully operational in 2021, the four power plants on the river will cumulatively generate 1,550 megawatts of electricity, enough to power a city or an estimated 1.5 million homes.

Since the 1970s, hydroelectricity has supplied 90 percent of Quebec's power needs.

The new Quebec provincial government of Francois Legault, with the backing of Prime Minister Justin Trudeau, has pledged to build even more dams once the Romaine project is completed.

The aim is to export as much power as possible to the United States, saying it would be "the biggest contribution that Quebec could make to the planet."

Other provinces also have big hydroelectric projects on the go, such as Newfoundland's Muskrat Falls, Manitoba's Keeyask and British Columbia's Site C.

Neighboring Ontario, meanwhile, is spending Can$25 billion to refurbish two aging nuclear power plants.

A Hydro-Quebec employee looks out over the spillway for the Romaine 3 hydroelectric dam in Quebec—the hope is to attract more and more US customers with the prospect of clean energy

Pierre-Olivier Pineau, an energy specialist at HEC university in Montreal, expressed doubt after visiting the Romaine project about the need for more power plants, pointing to Quebec's current surplus energy.

"In the northeastern United States, there is a great desire to decarbonize electricity production in New England or New York state, so there is a real opportunity for Quebec," he told AFP.

"La Romaine could provide this renewable energy."

However, more transmission lines connecting the stations to US buyers still need to be approved and built.

Explore further: Tajikistan launches giant dam to end power shortage

Related Stories

Tajikistan launches giant dam to end power shortage

November 16, 2018

Tajikistan on Friday inaugurates a $3.9 billion hydro-electric power plant, a mega project that will enable the impoverished country to eliminate domestic energy shortages and export electricity to Afghanistan and Pakistan.

Quebec wary of bitcoin gold rush

April 18, 2018

At the site of a former cocoa factory in Canada's Quebec province, tiny holes punctured in the walls of a warehouse allow fresh air to cool thousands of whirring processors connected by a tangle of wires.

Quebec to tax some tech firms

March 28, 2018

Quebec will start applying a sales tax to some internet companies such as Netflix and AirBnb starting in 2019, the government of the French speaking province said Tuesday.

Massive hydroelectric project faces test in Chile

May 9, 2011

A $3.2 billion hydroelectric project billed as key to satisfying Chile's growing energy needs faces a major hurdle Monday as an environmental panel decides whether or not to give it the green light.

Recommended for you

Uber filed paperwork for IPO: report

December 8, 2018

Ride-share company Uber quietly filed paperwork this week for its initial public offering, the Wall Street Journal reported late Friday.

0 comments

Please sign in to add a comment. Registration is free, and takes less than a minute. Read more

Click here to reset your password.
Sign in to get notified via email when new comments are made.