German port's future blowing in the wind
![Workers prepare a wind turbine steel tower before it is moved by a bridge crane at the offshore terminal of the Offshore Base Cuxhaven June 7, 2011. The small German port of Cuxhaven is betting its future on North Sea wind, promoting itself as a base for new offshore wind farms as the country embarks on a bid to scrap nuclear power. Workers prepare a wind turbine steel tower at the offshore terminal of the Offshore Base Cuxhaven](https://scx1.b-cdn.net/csz/news/800a/2011/workersprepa.jpg)
The small German port of Cuxhaven is betting its future on North Sea wind, promoting itself as a base for new offshore wind farms as the country embarks on a bid to scrap nuclear power.
Five-hundred-tonne tripods, meant to be sunk to the sea floor to support giant wind turbines, line the quays awaiting shipment out to sea.
"Wind power is the promise of an industrial future. Business used to be stagnant," says Hans-Joachim Stietzel, scientific director of the local economic development agency.
For this port of 52,000 inhabitants, which once lived off fish factories and retirement homes, Chancellor Angela Merkel's decision late last month for Germany to renounce nuclear power by 2022 is manna from heaven.
Cuxhaven, which was losing its importance as a harbour because of the development of giant container ships that prefer ports such as Hamburg or Rotterdam, decided to take up the windpower challenge as early as 2007.
It built a specialised terminal, with roads and platforms designed to take very heavy loads, and turned sheep pastures into industrial parks.
With parliament expected to vote later this month on abandoning nuclear power and the government promising five billion euros ($7 billion) to develop offshore electricity production, Cuxhaven is eyeing a golden opportunity.
"Of course this is going to help. But we didn't wait for the government to get on with the job," says engineer Rolf Bartelheim of Cuxhaven Steel Construction, a firm that set up shop here in 2009.
![A worker looks on as the section of a wind turbine steel tower is moved by a bridge crane at the offshore terminal of the Offshore Base Cuxhaven June 7, 2011. The small German port of Cuxhaven is betting its future on North Sea wind, promoting itself as a base for new offshore wind farms as the country embarks on a bid to scrap nuclear power. A worker looks on as the section of a wind turbine steel tower is moved by a bridge crane](https://scx1.b-cdn.net/csz/news/800a/2011/aworkerlooks.jpg)
Workers busy themselves around the giant tripods which will be sunk in waters from 20 to 40 metres (65 to 130 feet) deep.
The turbines will then stand 100 metres high with rotor spans of equal dimension, taller and wider than London's St. Paul cathedral.
"We have a two-to-three-year jump" on other German centres, such as Bremerhaven in the northwest, says Stietzel who believes nevertheless there will be "enough work to go around".
By 2030 Germany wants offshore wind power to provide 25,000 megawatts of power, the equivalent of 20 nuclear reactors.
Three offshore wind farms are currently operating in German waters, while some 20 more have been granted planning permission. Another 20 are planned.
![View of European construction giant Strabag's trial gravity foundation for offshore power plants at the Offshore Base Cuxhaven June 7, 2011. The trial involves stress tests simulating wind and tidal flow on the massive concrete base which would be deposited on the seabed rather than buried. European construction giant Strabag's trial gravity foundation for offshore power plants at the Offshore Base Cuxhaven](https://scx1.b-cdn.net/csz/news/800a/2011/europeancons.jpg)
Merkel recently inaugurated the country's first commercial wind farm, with 21 turbines set to supply electricity to more than 50,000 households, off the northeastern Baltic coast.
Germany has big plans for offshore "clean" energy, but it got off to a slow start compared to Britain and the Netherlands because of its very strict planning rules, which have only allowed turbines to set up in deep waters.
In the North Sea, this has made everything more difficult, from setting up the turbines to connecting them to the grid.
"Because of weather and safety concerns, we're happy if we can get 85 days in the year to go out to sea to set up the wind turbines," says Bartelheim.
Financing is also a problem, he says.
"The five billion promised by the state won't cover all the costs" at a time when private investors are reluctant to back such costly developments, he says.
The start-up cost of a wind farm is about one billion euros.
(c) 2011 AFP