Fukushima was 'man-made' disaster: Japanese probe

Jul 04, 2012 by Hiroshi Hiyama
Black smoke rises from reactor number three at the Fukushima nuclear power plant in March 21, 2011. The nuclear accident at Fukushima last year was a "man-made disaster" and not only due to the tsunami, a Japanese parliamentary panel said Thursday in its final report on the catastrophe.

Last year's nuclear accident at Fukushima was a man-made catastrophe and not only due to the tsunami that hit the plant, a Japanese parliamentary panel said Thursday in its final report on the disaster.

"The TEPCO Fukushima Nuclear Power Plant accident was the result of collusion between the government, the regulators and (plant operator) TEPCO, and the lack of governance by said parties," said the report by the Diet's Fukushima Nuclear Accident Independent Investigation Commission.

"They effectively betrayed the nation's right to be safe from nuclear accidents. Therefore, we conclude that the accident was clearly 'man-made'.

"We believe that the root causes were the organisational and regulatory systems that supported faulty rationales for decisions and actions, rather than issues relating to the competency of any specific individual."

The probe is the third of its kind in Japan since the world's worst nuclear crisis in a generation.

A little girl holds out her hands for a radiation scan at a screening center in Koriyama in Fukushima prefecture on March 22, 2011. Tens of thousands of people were evacuated from an area around the Fukukshima plant to avoid radiation contamination. Many have still not been allowed home, with some areas expected to be uninhabitable for decades.

An earlier report by plant operator Tokyo Electric Power (TEPCO) had all but cleared the huge utility, saying the size of the earthquake and tsunami was beyond all expectations and could not reasonably have been foreseen.

But an independent group of scholars and journalists, who reported their findings in February, said TEPCO could and should have done more.

It also said that had the company had its way, its staff would have been evacuated from the crippled plant and the catastrophe could have spiralled even further out of control.

The findings published on Thursday call for further investigation into the impact of the 9.0 magnitude earthquake -- as opposed to the towering tsunami -- on the reactors at Fukushima.

"As for direct cause of the accident, the commission reached the conclusion that we cannot definitely say any devices that were important for safety were not damaged by the earthquake," it said.

"We cannot rule out the possibility that a small-scale LOCA (loss-of-coolant accident) occurred at the reactor No. 1 in particular."

Although many scientists and activists have questioned the dominant narrative that cooling systems were knocked out by the rising waters, the government and TEPCO have been unwilling to say the reactors were damaged by the initial earthquake.

Tectonically-volatile Japan has a network of nuclear reactors that, until Fukushima, had supplied around a third of the nation's electricity.

Graphic showing what happened at the Fukushima nuclear powerplant in March 2011, when a tsunami triggered meldowns that spewed radioactivity and forced tens of thousands of residents to flee.

The nuclear industry has long boasted of its many safeguards against earthquakes, but much recent public opposition to atomic power has focused on the vulnerability of plants, especially those that sit near seismic faults.

The report said "it is considered that TEPCO management knew about delays in anti-quake works and postponement of tsunami measures and were aware that the Fukushima Daiichi (number one plant) was vulnerable."

TEPCO also failed to act promptly in the early stages of the disaster, the panel concluded, but added: "This should not be attributed to individuals... at the plant but the structural problems of TEPCO."

The administration of then premier Naoto Kan hampered operations as the disaster unfolded, the report said, and did not use a logical chain of command.

"The prime minister's office was supposed to contact the plant operator through an on-the-spot taskforce. But... issued direct instructions to TEPCO head office and the accident site, confusing the command line."

Japan's nuclear watchdog was remiss because it did not force TEPCO to act, even when it knew things were going wrong, the report said.

"The Nuclear Industrial Safety Agency (NISA) knew TEPCO was postponing taking measures but did not give clear instructions," it said, adding NISA "was unprepared for a disaster whose scale exceeded past accidents."

Explore further: Qi wireless charging standard offers more design freedom

add to favorites email to friend print save as pdf

Related Stories

Japan says plant clean-up will take decades

Jul 09, 2011

Japan's prime minister said on Saturday the decommissioning of the crippled Fukushima nuclear plant would take decades, in the first government announcement of a long-term timeframe for the clean-up.

Japan vows to continue nuclear plant exports

Aug 05, 2011

Japan said Friday it will continue exporting atomic power plants, despite uncertainty over its own use of them as it continues to grapple with a crisis at the tsunami-hit Fukushima nuclear plant.

TEPCO to open second Fukushima reactor building

Jun 19, 2011

Tokyo Electric Power Co. said it will open a second reactor building at the stricken Fukushima nuclear power plant to send repair crews inside for the first time since it was crippled.

Recommended for you

Qi wireless charging standard offers more design freedom

8 hours ago

Wireless charging is getting a new technology treatment which offers more design freedom. The Wireless Power Consortium's advance in its Qi wireless charging standard means that phones and chargers will no ...

'Wetting' a battery's appetite for renewable energy storage

13 hours ago

Sun, wind and other renewable energy sources could make up a larger portion of the electricity America consumes if better batteries could be built to store the intermittent energy for cloudy, windless days. Now a new material ...

New system to optimize public lighting power consumption

13 hours ago

In order to meet the efficiency requirements of the latest public lighting regulations, researchers from the School of Industrial Engineers of Universidad Politécnica de Madrid (UPM), in collaboration with ...

Many tongues, one voice, one common ambition

Jul 31, 2014

There is much need to develop energy efficient solutions for residential buildings in Europe. The EU-funded project, MeeFS, due to be completed by the end of 2015, is developing an innovative multifunctional and energy efficient ...

Panasonic, Tesla to build big US battery plant

Jul 31, 2014

(AP)—American electric car maker Tesla Motors Inc. is teaming up with Japanese electronics company Panasonic Corp. to build a battery manufacturing plant in the U.S. expected to create 6,500 jobs.