Corps of Engineers completes Army's largest solar array installation

Corps of Engineers completes Army's largest solar array installation
This aerial view of the solar photovoltaic array at White Sands Missile Range, N.M., was taken, Jan. 8, 2013. The panels cover 42 acres and provide more than four megawatts of electricity to the base. Credit: Solaria

The largest solar power system in the U.S. Army is coming online at White Sands Missile Range, N.M., and officials gathered Jan. 16, to mark the occasion with a ribbon-cutting ceremony.

The Energy Savings Performance Contract, or ESPC, project, awarded and managed by the U.S. Army Engineering and Support Center, Huntsville, provides the sprawling desert base with a new 4.465 megawatt solar photovoltaic system, guarantees energy savings of 35,358M British thermal units per year, and reduces their by 10 percent, said Wesley Malone, Huntsville Center project manager.

"To date this is the largest in the Army," said Michael Norton, Huntsville Center Energy Division chief. "Projects like this are important because the impact of rising energy prices on installations has resulted in an adverse increase of utility budgets spent on existing, often inefficient or outdated equipment."

"ESPC projects provide energy efficient equipment resulting in a lower utility consumption," Norton said. "Lower utility consumption reduces the DOD utility bills and assists in meeting federal mandates."

ESPC brings in private party financing for at Defense Department garrisons. An Energy Savings Contractor, ESCO, provides capital and expertise to make on government facilities to significantly reduce Army energy, in exchange for a portion of the generated savings. In the case of the White Sands , Siemens Government Technologies, Inc., of Arlington, Va. was selected as the ESCO.

Along with being the largest solar project, there's another first in how the system at White Sands Missile Range was funded.

"We used an Services Agreement for the photovoltaic equipment along with the ESPC concept which was a first for the Army," said Will Irby, Huntsville Center ESPC Program Manager.

An ESA is an arrangement whereby a third party owns, operates and maintains the power generation system and provides electricity to the customer. This third-party ownership mechanism allowed for a significant tax grant from that reduced the project cost by $6.1M, Irby said.

Construction of the $16.5M system started in July and was completed in December.

Provided by U.S. Army

Citation: Corps of Engineers completes Army's largest solar array installation (2013, January 25) retrieved 24 April 2024 from https://phys.org/news/2013-01-corps-army-largest-solar-array.html