Japan to start building underground ice wall at Fukushima (Update)

Jun 02, 2014
A TEPCO employee at the control room of the Fukushima nuclear power plant at Okuma town in Fukushima prefecture on May 21, 2014

Japan on Monday started work on an underground ice wall at the crippled Fukushima nuclear plant, freezing the soil under broken reactors to slow the build-up of radioactive water, officials said.

The wall is intended to block groundwater from nearby hillsides that has been flowing under the plant and mixing with polluted water already there.

The Nuclear Regulation Authority, the national watchdog, last week authorised construction of the ice wall at Fukushima Daiichi, owned and operated by Tokyo Electric Power (TEPCO).

"We started construction of the frozen earth wall this afternoon," a TEPCO official told a news conference in Tokyo.

The government-funded scheme will see 1,550 pipes laid deep in the soil through which refrigerant will be piped to create the 1.5-kilometre (0.9-mile) frozen wall that will stem the inflow of groundwater.

"We plan to end all the construction work in March 2015 before starting trial operations," the company official said, adding that the ice wall could be fully operational several months after construction was completed.

The idea of freezing a section of soil, which was proposed for Fukushima last year, has previously been used to build tunnels near watercourses.

However, scientists point out that it has not been done on this scale before nor for the proposed length of time.

Graphic outlining schemes to divert groundwater at Japan's crippled Fukushima nuclear plant to prevent radioactive contamination of sea water

Coping with the huge—and growing—amount of water at the tsunami-damaged plant is proving to be one of the biggest challenges for TEPCO, as it tries to clean up the mess after the worst nuclear disaster in a generation, in which three reactors went into meltdown.

As well as all the water used to keep broken reactors cool, the utility must also deal with water that makes its way along subterranean watercourses from mountainsides to the sea.

Last month TEPCO began a bypass system that diverts groundwater into the sea to try to reduce the volume of contaminated water.

Full decommissioning of the plant at Fukushima is expected to take several decades.

An area around the site remains out of bounds, and experts warn that some settlements may have to be abandoned because of high levels of radiation following the 2011 accident.

Explore further: Japan to create underground ice wall at crippled nuclear plant

add to favorites email to friend print save as pdf

Related Stories

Steam seen at Fukushima reactors: TEPCO

Sep 13, 2013

Vapour has begun rising again from a reactor at the Fukushima nuclear power plant, more than two-and-a-half years after its core melted down, the site's Japanese operator said Friday.

Japan to boost surveys off Fukushima: report

Sep 14, 2013

Japan's nuclear authority plans to conduct radiation contamination surveys at 600,000 points on the seabed off the crippled Fukushima nuclear plant, up from 200 places so far, a report said Saturday.

Radioactive water 'may have leaked' from Fukushima

Apr 06, 2013

Radioactive water may have leaked into the ground from a tank at the Fukushima Daiichi nuclear power plant, the operator said on Saturday, the latest in a series of troubles at the crippled facility.

Recommended for you

Should the Japanese give nuclear power another chance?

Oct 24, 2014

On September 9, 2014, the Japan Times reported an increasing number of suicides coming from the survivors of the March 2011 disaster. In Minami Soma Hospital, which is located 23 km away from the power plant, ...

UK wind power share shows record rise

Oct 24, 2014

The United Kingdom wind power production has been enjoying an upward trajectory, and on Tuesday wind power achieved a significant energy production milestone, reported Brooks Hays for UPI. High winds from Hurricane Gonzalo were the force behind wind turbines outproducing nuclear power ...

Global boom in hydropower expected this decade

Oct 24, 2014

An unprecedented boom in hydropower dam construction is underway, primarily in developing countries and emerging economies. While this is expected to double the global electricity production from hydropower, it could reduce ...

User comments : 2

Adjust slider to filter visible comments by rank

Display comments: newest first

antialias_physorg
5 / 5 (1) Jun 02, 2014
Anyone willing to take bets whetherthis works (and if so - for any kind of duration)?

Sounds like a hare-brained scheme to me. And a power (and money) hungry one at that.
bluehigh
not rated yet Jun 02, 2014
No to that bet, thanks. I agree with you antialias. Although ground soil freezing seems to have been successfully used in a few mining projects, mostly for ease of excavation, I find no source for successful long term implementation. Most longer term proposed projects collapsed due to financial problems before even paying the ongoing maintenance. I am also sceptical that the so called ice wall will prevent radiation transfer. Nevertheless, lets hope it works because its a serious mess at it stands.