Finnish nuclear reactor 'may be seven years late'

Feb 11, 2013
The Olkiluoto 3 nuclear reactor. Finnish electricity company TVO said on Monday that an EPR nuclear reactor being built by Areva and Siemens may not be ready until 2016, after an initial 2009 completion target

Finnish electricity company TVO said on Monday that an EPR nuclear reactor being built by Areva and Siemens may not be ready until 2016, contradicting Areva's claims that it would be completed in 2014.

"Based on the recent progress reports received from the plant supplier ... TVO is preparing for the possibility that the start of the regular of Olkiluoto 3 unit may be postponed until the year 2016," the company said in a statement.

In August, TVO said that the reactor being built in southwestern Finland would not be ready to produce electricity in 2014, but declined to give a new completion date.

Areva president Luc Oursel told a Finnish business daily in September that the group was on track to complete the project in 2014.

TVO lacked "an adequate schedule update", but about 75 percent of the installation works had been completed, the Finnish company's project manager, Jouni Silvennoinen, said Monday.

"Although TVO is not pleased with the situation and repeated challenges with the project scheduling, the works are proceeding," he said.

Monday's announcement marked only the latest in a string of setbacks for the construction project, which began in 2005, with the reactor initially supposed to begin producing electricity in 2009.

The Finnish EPR, or European Pressurized Reactor, is an example of so-called third-generation developed by Areva.

It is set to have a capacity of 1,600 , and was first delayed until November 2010, then to December 2011 and then to August 2014.

Explore further: Dutch seek to harness energy from salt water mix

add to favorites email to friend print save as pdf

Related Stories

Fukushima raises questions about new Finnish reactor

Jun 21, 2011

More than 5,000 hard-hat workers swarm over a sprawling nuclear facility in western Finland to build OL3 -- touted as the safest nuclear reactor in the world -- a claim which has come under scrutiny following ...

Nuclear giant Areva to post 'significant' loss'

Dec 11, 2011

French state-owned nuclear giant Areva is to announce significant losses when it unveils its new corporate strategy this week, Industry Minister Eric Besson said on Sunday.

Recommended for you

Dutch seek to harness energy from salt water mix

22 minutes ago

Dutch researchers are seeking to add a new, largely untapped renewable energy source to the world's energy mix with the opening of a "Blue Energy" test facility on Wednesday.

Are electric cars greener? Depends on where you live

17 hours ago

Long thought a thing of the future, electric cars are becoming mainstream. Sales in the United States of plug-in, electric vehicles nearly doubled last year. Credible forecasts see the number rising within ...

Building a better battery

19 hours ago

Imagine an electric car with the range of a Tesla Model S - 265 miles - but at one-fifth the $70,000 price of the luxury sedan. Or a battery able to provide many times more energy than today's technology ...

Researchers find way to turn sawdust into gasoline

23 hours ago

Researchers at KU Leuven's Centre for Surface Chemistry and Catalysis have successfully converted sawdust into building blocks for gasoline. Using a new chemical process, they were able to convert the cellulose ...

Nanodot team aims to charge phones in less than a minute

Nov 25, 2014

The world of smartphone users, which is a very large base indeed, is ripe for better battery solutions and an Israel-based company has an attractive solution in store, in the form of nanodot batteries that ...

User comments : 3

Adjust slider to filter visible comments by rank

Display comments: newest first

JRi
3 / 5 (2) Feb 11, 2013
This project is a disaster. Workers are from several different countries, where the contractors just can get them at lowest cost, and they can't even communicate properly with each other due to language barriers.
VendicarE
5 / 5 (1) Feb 11, 2013
Finnish can't finish.
Eikka
not rated yet Feb 11, 2013
Finnish can't finish.


You mean the French can't?

Please sign in to add a comment. Registration is free, and takes less than a minute. Read more

Click here to reset your password.
Sign in to get notified via email when new comments are made.