The Olkiluoto 3 nuclear reactor. Finnish electricity company TVO said on Monday that an EPR nuclear reactor being built by Areva and Siemens may not be ready until 2016, after an initial 2009 completion target

Finnish electricity company TVO said on Monday that an EPR nuclear reactor being built by Areva and Siemens may not be ready until 2016, contradicting Areva's claims that it would be completed in 2014.

"Based on the recent progress reports received from the plant supplier ... TVO is preparing for the possibility that the start of the regular of Olkiluoto 3 unit may be postponed until the year 2016," the company said in a statement.

In August, TVO said that the reactor being built in southwestern Finland would not be ready to produce electricity in 2014, but declined to give a new completion date.

Areva president Luc Oursel told a Finnish business daily in September that the group was on track to complete the project in 2014.

TVO lacked "an adequate schedule update", but about 75 percent of the installation works had been completed, the Finnish company's project manager, Jouni Silvennoinen, said Monday.

"Although TVO is not pleased with the situation and repeated challenges with the project scheduling, the works are proceeding," he said.

Monday's announcement marked only the latest in a string of setbacks for the construction project, which began in 2005, with the reactor initially supposed to begin producing electricity in 2009.

The Finnish EPR, or European Pressurized Reactor, is an example of so-called third-generation developed by Areva.

It is set to have a capacity of 1,600 , and was first delayed until November 2010, then to December 2011 and then to August 2014.

Explore further: Many tongues, one voice, one common ambition

add to favorites email to friend print save as pdf

Related Stories

Fukushima raises questions about new Finnish reactor

Jun 21, 2011

More than 5,000 hard-hat workers swarm over a sprawling nuclear facility in western Finland to build OL3 -- touted as the safest nuclear reactor in the world -- a claim which has come under scrutiny following ...

Nuclear giant Areva to post 'significant' loss'

Dec 11, 2011

French state-owned nuclear giant Areva is to announce significant losses when it unveils its new corporate strategy this week, Industry Minister Eric Besson said on Sunday.

Recommended for you

Qi wireless charging standard offers more design freedom

4 hours ago

Wireless charging is getting a new technology treatment which offers more design freedom. The Wireless Power Consortium's advance in its Qi wireless charging standard means that phones and chargers will no ...

'Wetting' a battery's appetite for renewable energy storage

9 hours ago

Sun, wind and other renewable energy sources could make up a larger portion of the electricity America consumes if better batteries could be built to store the intermittent energy for cloudy, windless days. Now a new material ...

New system to optimize public lighting power consumption

10 hours ago

In order to meet the efficiency requirements of the latest public lighting regulations, researchers from the School of Industrial Engineers of Universidad Politécnica de Madrid (UPM), in collaboration with ...

Many tongues, one voice, one common ambition

Jul 31, 2014

There is much need to develop energy efficient solutions for residential buildings in Europe. The EU-funded project, MeeFS, due to be completed by the end of 2015, is developing an innovative multifunctional and energy efficient ...

Panasonic, Tesla to build big US battery plant

Jul 31, 2014

(AP)—American electric car maker Tesla Motors Inc. is teaming up with Japanese electronics company Panasonic Corp. to build a battery manufacturing plant in the U.S. expected to create 6,500 jobs.

User comments : 3

Adjust slider to filter visible comments by rank

Display comments: newest first

JRi
3 / 5 (2) Feb 11, 2013
This project is a disaster. Workers are from several different countries, where the contractors just can get them at lowest cost, and they can't even communicate properly with each other due to language barriers.
VendicarE
5 / 5 (1) Feb 11, 2013
Finnish can't finish.
Eikka
not rated yet Feb 11, 2013
Finnish can't finish.


You mean the French can't?