Infrastructure megaprojects that are delivered late and over budget aren't necessarily failures – here's why

Infrastructure megaprojects that are delivered late and over budget aren't necessarily failures – here's why
Credit: AI-generated image (disclaimer)

If an infrastructure megaproject is completed late and over budget, it is widely judged to be unsuccessful. For instance, the delay to Crossrail, a new train line across London and the south east of England, has been labeled "appalling news." Crossrail is also projected to cost nearly £4 billion more than its original budget.

My research on projects like these, however, suggests that this narrow framing is not always appropriate.

Instead of comparing the original cost and time estimate of these megaprojects against the final result, it may be more important to think about the the value delivered by these infrastructure across their life time and the sustainability of the project—and whether this is worth the final cost and time taken. This is more difficult, but also far more meaningful.

Measuring success

Framing the success of infrastructure megaprojects around whether they are completed on time and to budget is a considerable limitation that may warp our understanding of success. If a bridge is built to link two towns, people traveling between them using the new bridge will save time and fuel over a longer route. A new transport route may boost the nearby economy, creating local jobs. Cost-time framing does not capture this.

In order to take these results into account, large projects are often subject to a . This is the comparison of the involved in building and operating the infrastructure against its benefits.

For a simple project like a primary school, cost and benefit are easy to establish. On the cost side is the construction and operations. In terms of benefits, a certain number of children will be educated, and a certain number of jobs will be created.

However, the benefits of a large infrastructure project, like a bridge, are very hard to predict and extremely subjective. One of the towns linked by the bridge may be affluent and another deprived, so by connecting the two together and reducing commuting times, the deprived town will receive a boost. People living there may have better access to jobs, and the town itself may become regenerated. However, this might also lead to house prices rising and subsequent gentrification, displacing previous communities.

Infrastructure megaprojects that are delivered late and over budget aren't necessarily failures – here's why
Credit: AI-generated image (disclaimer)

The original cost estimate to build Sydney Opera House was AU$7 million (£3.9 million): the final cost was AU$102 million. Another project over budget—and ten years late.

However, more than 10.9 million people visit the opera house every year. Remarkably, the 2018-19 total audience attendance for performing arts events was 1.4 million, so the remaining 9.5 million people went to see the opera house itself. The opera house is a major positive boost for Australia's economy and culture.

Value and sustainability

A better way of evaluating infrastructure megaprojects would be to investigate their value and sustainability. It is worth considering which people or organizations can claim a share of the value of a project. For instance, the bridge could be free to use for electric vehicles or, before building the bridge, plans could be made for parks and places where people can socialize.

People use infrastructure in different ways. Instead of starting from the infrastructure, projects should begin by considering people and how the project can be planned, designed and delivered for them. For instance, the concerns of local people about disruption or environmental damage should not be dealt with as an afterthought, but be considered from the inception of a project.

The second point is about sustainability. A project's sustainability needs to be considered over its lifetime. Infrastructure takes years to build, but should last centuries. In addition, the building and running of the will require energy—is this affordable and clean, or an expensive and dirty technology?

Furthermore, we know that men and women work a different number of hours, at different times of the day, in different places. A sustainability assessment should weigh up if the infrastructure is promoting gender equality, or increasing the divide. Whether modern slavery is involved in building the infrastructure must also be considered.

Similarly, we should look at positive impacts from a point of view, such as the creation of secure jobs, and the promotion of innovation in technology.

Cost- performance might be relevant in the short term, particularly for the organizations involved in the delivery of the —but there is a much bigger picture to consider.

Provided by The Conversation

This article is republished from The Conversation under a Creative Commons license. Read the original article.The Conversation

Citation: Infrastructure megaprojects that are delivered late and over budget aren't necessarily failures – here's why (2020, October 6) retrieved 25 June 2024 from https://phys.org/news/2020-10-infrastructure-megaprojects-late-necessarily-failures.html
This document is subject to copyright. Apart from any fair dealing for the purpose of private study or research, no part may be reproduced without the written permission. The content is provided for information purposes only.