November 5, 2018

This article has been reviewed according to Science X's editorial process and policies. Editors have highlighted the following attributes while ensuring the content's credibility:

TVA announces solar installations being built for Facebook

Tennessee and Alabama will get their largest solar power projects yet, to supply a Facebook data center with 100 percent renewable energy.

Officials with the Tennessee Valley Authority announced an agreement with two developers to build the electricity providers.

John Bradley, TVA's of Economic Development, said Friday that First Solar in Colbert County, Alabama and NextEra Energy Resources in Lincoln County, Tennessee, will produce 377 megawatts between them to supply Facebook's data center in Huntsville, Alabama.

Doug Perry, TVA vice president of Commercial Energy Solutions, says the federal utility plans on investing $8 billion in renewable energy over the next 20 years.