Tech bugs plague federal projects

Dec 05, 2013 by Joseph Tanfani

t was an ambitious federal technology project, tying together a string of government databases in one Web portal. But the launch was a giant mess: contract missteps, broken deadlines, cost overruns. Users complained the site was balky and unworkable.

That was the rocky rollout last year of SAM.gov, a General Services Administration project intended to combine nine different contracting databases. The site was delayed two months and, even then, performance was so poor that it had to be taken down for repairs. In March, the GSA apologized after finding a flaw that could have exposed users' personal information.

Another federal website, the spectacularly flawed HealthCare.gov, has created a political crisis for the Obama administration. But as SAM.gov and other projects demonstrate, technology failures have become the rule in the federal government, not the exception.

Websites crash, attempts to modernize systems founder and military systems costing hundreds of millions are abandoned before ever being used.

The Obama administration has tried to confront the problem, appointing top technology officers who scrapped and consolidated some flagging projects and pushed for more agile procedures. But the reforms have been modest.

Last month, Obama acknowledged that the administration had not been able to fix a procurement system that he said was "just generally not very efficient."

"In fact, there's probably no bigger gap between the private sector and the public sector than IT," he said.

Experts point out that troubled projects aren't unusual in either. But the government's problems, involving taxpayer money, are pervasive and add up to billions in waste. Washington will spend more than $76 billion this year on information technology. A federal report in January found that 700 projects, accounting for $12.5 billion, were in trouble.

"Clearly the federal IT system is broken," said Michael Krigsman, an industry analyst who is often hired to analyze project failures. The problems seen with HealthCare.gov are not unique, he said.

"There are whole strings of failed IT projects where everybody points fingers at everybody else, and there's no one who ultimately takes responsibility."

The problems start with a byzantine contracting system that matches up poorly with the fast-evolving information world.

In the time it takes federal agencies to figure out what they need and get Congress to appropriate money, the technology can become obsolete or the costs increase dramatically.

The appropriations process, said one tech industry lobbyist, is stuck in a "horse and buggy" era.

"It's almost impossible for the government to find what it wants and get Congress and the (Office of Management and Budget) to buy that thing in a timely fashion," added Trey Hodgkins, senior at the Information Technology Industry Council, a trade group.

Another problem: Years of budget cuts and outsourcing have left many federal agencies short on technology talent. They are often slow in defining what they need at the start of a project, then unable to manage trouble when it happens.

A year ago, the Air Force scrapped a system that was supposed to improve supply management. The project had run for seven years at a cost of more than $1 billion. Afterward, a review team found it had suffered from mismanagement, a churn in directors and "simply an underestimation of the sophistication needed in tackling the enormous and complex effort."

In the case of SAM.gov, or System for Award Management, the GSA in 2008 began to consolidate databases into one big Web portal for use by private companies looking for government business as well as the government and civilian employees who hand out those contracts. The agency chose IBM Federal as the main contractor, giving the company $74.4 million over eight years.

But the GSA seriously underestimated costs. The agency thought IBM was providing the computers and software to host the website, but later realized officials had left that out of the contract, according to a report last year by the Government Accountability Office. They had to pay IBM another $38 million.

Meanwhile, Congress was slow to come up with extra money, the GAO found, leading to further delays and still-higher expenses to keep the old systems running.

Just as with HealthCare.gov, the SAM system proved to be buggy in late testing; the GSA delayed the launch, but that wasn't long enough to fix the problems.

In a statement, the GSA said the system was much improved, with fewer errors and shorter wait times. IBM said, "The system has been up and running successfully for the past year and IBM continues to support and innovate as part of the ongoing contract."

People from the technology world who have worked in the administration say the contracting process is inevitably tilted toward a few giant companies that can assemble experts in writing proposals - and who often file protests when things don't go their way.

"It's people with the best lawyers, not people with the best programmers," said Clay Johnson, chief executive of the nonprofit Department of Better Technology. "When your legal team becomes part of your sales force, you know you've got a problem."

Inside the agency building HealthCare.gov, the problems soon became obvious. The design of the website was supposed to be locked down by early 2012, one of the milestones that "must be completed to ensure the (exchange) will be ready," according to a contract document. But requirements kept shifting.

A consultant report from this spring said the design was "still presumed to be open" with six months to go, leading to "materially higher risk of system instability."

"It's like trying to build an airplane while you're flying it," said Dan Schuyler, former director of technology for the Utah Health Insurance Exchange and now a director with Leavitt Partners, a healthcare consulting firm. The Medicare and Medicaid agency that oversaw HealthCare.gov didn't have the capacity to run the project and tried to "build it from the ground up" after the law was passed, he said.

Daniel Goure, vice president of the Lexington Institute, a nonprofit policy research group based in Arlington, Va., said the health care site was "one you could have predicted would fail."

"Too many requirements, too many players, government trying to be in charge, starting too late - they were guaranteed not to make it on time," he said. "How come nobody told the government, you are riding for an incredible fall on this one?"

Explore further: Oracle helping to fix Obama's healthcare site

5 /5 (2 votes)
add to favorites email to friend print save as pdf

Related Stories

US asks contractor to lead health website repairs

Oct 25, 2013

The Obama administration said Friday that dozens of problems had been found in the website at the center of a landmark health care overhaul, and a private company has been asked to lead the repairs. Officials ...

Oracle helping to fix Obama's healthcare site

Oct 31, 2013

The Obama administration has recruited engineers from several prominent technology companies to help fix the technological problems preventing people from signing up for government-mandated health insurance.

US health law insurance site delayed one year (Update)

Nov 27, 2013

The Obama administration is delaying yet another aspect of its troubled health care law, putting off until next November the launch of an online portal to the health insurance marketplace for small businesses until the hobbled ...

White House: On track for health care website goal

Dec 01, 2013

The Obama administration says it will meet its self-imposed deadline of fixing the troubled federal government health care website, a key component of the president's signature domestic initiative. The stakes are high for ...

Recommended for you

US official: Auto safety agency under review

Oct 24, 2014

Transportation officials are reviewing the "safety culture" of the U.S. agency that oversees auto recalls, a senior Obama administration official said Friday. The National Highway Traffic Safety Administration has been criticized ...

Christian Bale to play Apple's Steve Jobs

Oct 23, 2014

Oscar-winner Christian Bale—best known for his star turn as Batman in the blockbuster "Dark Knight" films—will play Apple co-founder Steve Jobs in an upcoming biopic.

How to find a submarine

Oct 23, 2014

Das Boot, The Hunt for Red October, The Bedford Incident, We Dive At Dawn: films based on submariners' experience reflect the tense and unusual nature of undersea warfare – where it is often not how well ...

Government ups air bag warning to 7.8M vehicles (Update)

Oct 22, 2014

The U.S. government is now urging owners of nearly 8 million cars and trucks to have the air bags repaired because of potential danger to drivers and passengers. But the effort is being complicated by confusing ...

User comments : 3

Adjust slider to filter visible comments by rank

Display comments: newest first

geokstr
not rated yet Dec 09, 2013
It was just revealed a couple days ago that some federal agencies still use floppy disks. When were those surpassed by newer technology again, like 1870?
PolishKnightUSA
not rated yet Dec 16, 2013
In answer to your question, geokstr, it's perhaps reasonable that some federal agencies will use floppys when they have legacy data stored that they need retrieved. It's reminiscent of the final scene in Raiders of the Lost Ark with that vast warehouse. It's useful to keep this legacy technology around to read old stuff.

Regarding problems with scoping the project: Companies deliberately play a game of promising the moon, delaying the project, and then mucking it up so they get paid to fix it. Reminds me of a dentist that I left. They love change orders. That said, if NASA programmers could put a man on the moon, why can't IBM build a website in a few months or even years? Hmmm?

Even before the days of object oriented programming, work could be done in parallel with a large contingent of QUALITY programmers. Note the emphasis on quality: If they produce buggy code, then the project will not only fail upon launch but will take forever to fix.
dencopeland
not rated yet Dec 30, 2013
As it turns out, it's congressional inaction and underfunding that requires the National Archives to continue to receive floppy disks. It's a 'race to the bottom' situation where the Archives must keep the capability to read media from the lowest common denominator agency that's required to archive federal records.

Read more at: http://www.blogge...postname