Toothed giant rips through Alps despite rail link protests

December 6, 2018 by Céline Cornu
When finished, the tunnel on the Lyon-Turin train line is expected to stretch for nearly 60 kilometres across the French-Italian border

There is a fierce nip in the air outside, but inside the temperature is almost tropical and the further you advance into the dark, the louder the noise becomes.

This is the heart of the Lyon to Turin high-speed train link, where a boring machine is chomping through the earth, oblivious to the row within Italy's populist government over the project's future.

Underground in Saint-Martin-La Porte, in south-east France, some 20 workers are swarming around the mechanical beast in protective helmets, boots, noise-cancelling earmuffs and goggles.

Beyond them labours the vast cutter, with 70 steel toothed wheels driven by generators as powerful as eight Formula One engines.

The finished tunnel is expected to stretch nearly 60 kilometres (37 miles), between Saint-Jean-de-Maurienne in the Savoy region and Susa in Piedmont, with 45 of those kilometres in France and the other 12.5 in Italy.

From 2030, trains whizzing along this line would replace hundreds of thousands of lorries which currently rumble across the Alps.

The two-way route will incldue 162 kilometres of tunnel space overall and workers have dug 25 kilometres so far, Piergiuseppe Gilli, construction manager at the Franco-Italian company Telt, tells AFP.

The 11-metre wide tunnel borer digs for 16 hours a day and the remaining eight are spent on maintenance
'Federica' the borer

Some 800 people work on the site in all. On the stretch between Saint-Martin-La Porte and La Praz, work progresses on two fronts.

The type of rock in the Lyon direction demands the use of traditional methods, such as explosives, while a tunnel boring machine (TBM) nicknamed "Federica" ploughs the other way, towards Italy.

Six of the nine kilometres of this section have already been dug, including 5.5 by the TBM, which "is advancing at a rate of 15 to 18 metres (50 to 60 feet) per day, or 400 metres per month"—better than the 250 metres a month originally planned, said Francesco Gamba, works director at Saint-Martin-La Porte.

Federica is huge: 11 metres wide and 135 metres long. She digs for 16 hours a day, and the remaining eight are spent on her maintenance.

Her heavy steel wheels—each weighing 100 kilograms (nearly 16 stone each)—need to be removed and replaced four times a day by hand, because the blades wear out quickly.

"You also need to replenish the oil and other liquids, and do the progress reports," says Gamba.

The atmosphere in the tunnel is oppressive, with deafening noise and artificial light

Up on bridges, drillers check the rock's physical characteristics, from the presence of clay or quartz to water or gas.

The speed is controlled by technicians who have eyes on Federica's process via video streamed to the site cabin, while the rubble produced is removed via conveyor belt.

Anti-tunnel protest

The voussoirs, blocks of concrete that form the tunnel's sides and ceiling, are brought in on rubber-tired trains and put into place using a sort of giant suction pad, with resin then injected into the gaps between them.

Some 48,000 blocks will be used for these nine kilometres alone.

The atmosphere in the tunnel is oppressive: the noise is deafening, the light artificial, and the exit and fresh air a long way off.

Guillaume Nonfoux, a 31-year old tunneller, says those who work under rock are "like a family" where the key is "mutual help".

Workers are digging a French section of the tunnel on two fronts, one of them based at this site in Saint-Martin-la-Porte

But out on the surface, the tunnel has divided communities and sparked protests.

Some 40,000 people rallied in favour of the project last month in Turin, and those opposed have planned a big demonstration for Saturday.

"This valley already houses a lot of infrastructure, this project is useless. Traffic between France and Italy has dropped significantly compared to during the economic boom," argues Susa mayor Sandro Plano.

But if the high-speed link is scrapped, "we cannot leave the dug tunnels without maintenance," Gilli warns.

"We'll need to prepare a 'restoration' project, which will have to be approved both in France and in Italy".

Explore further: Elon Musk's Boring Company nixes one L.A. tunnel, moves onto next project

Related Stories

Meet TIM, the LHC tunnel's robot

November 27, 2016

The name's TIM, Robot TIM – meet the spy patrolling the 27-km tunnel of the Large Hadron Collider (LHC). TIM, the Train Inspection Monorail, is a mini vehicle transporting a set of instruments along tracks suspended from ...

Elon Musk presents underground LA tunnel project

May 18, 2018

Entrepreneur Elon Musk has given updated details of a project to build high-speed transport tunnels underneath Los Angeles in a bid to combat traffic and said he wanted to work with the city's subway operator.

Recommended for you

Understanding dynamic stall at high speeds

December 18, 2018

When a bird in flight lands, it performs a rapid pitch-up maneuver during the perching process to keep from overshooting the branch or telephone wire. In aerodynamics, that action produces a complex phenomenon known as dynamic ...

Pushing lithium ion batteries to the next performance level

December 13, 2018

Conventional lithium ion batteries, such as those widely used in smartphones and notebooks, have reached performance limits. Materials chemist Freddy Kleitz from the Faculty of Chemistry of the University of Vienna and international ...

Uber filed paperwork for IPO: report

December 8, 2018

Ride-share company Uber quietly filed paperwork this week for its initial public offering, the Wall Street Journal reported late Friday.

0 comments

Please sign in to add a comment. Registration is free, and takes less than a minute. Read more

Click here to reset your password.
Sign in to get notified via email when new comments are made.