Sentinel-1 controllers ready for hectic first days

Mar 26, 2014
Main control room. Credit: ESA/J.Mai

Following a spectacular launch, Sentinel-1A's first few days in orbit will be some of the most complex in recent memory. Mission control teams will work around the clock to nurse the satellite through its early critical hours in space.

As part of Europe's Copernicus programme, ESA's Sentinel-1A is the first of a two-satellite that will scan land and oceans using an advanced radar to deliver imagery regardless of weather.

Sentinel-1A will be lofted into orbit by a Soyuz launch vehicle from Europe's Spaceport in Kourou, French Guiana at 21:02 GMT (23:02 CEST) on 3 April. The satellite will separate from the upper stage just under 25 minutes later at an altitude of about 690 km.

Separation marks the start of 'LEOP' – the crucial launch and early orbit phase – when mission controllers at ESOC, ESA's operations centre in Darmstadt, Germany, assume responsibility for the satellite.

During the first few orbits, ground control teams will deploy two solar wings – to provide the satellite with electrical power – and open the two radar antenna wings.

"This deployment sequence is much more complex than I've experienced on previous missions, and requires a total of 10 interleaved solar array and radar deployment stages," says Ian Shurmer, Spacecraft Operations Manager.

This video is not supported by your browser at this time.

"Each of the two separate solar wings must be released and deployed and then rotated towards the Sun. Similarly, each of the radar antenna wings will be released and taken through two separate partial and complete deployment stages. These deployment stages are interleaved to avoid physical clashes."

LEOP marks the critical first hours

This complex sequence requires that each step be individually commanded by engineers on the ground during the first 11 hours of flight, rather than being executed automatically, as is usual with simpler deployment designs.

The LEOP period will also see engineers working around the clock to switch on startrackers and GPS receivers and check out overall satellite health.

"By the third day, we'll transition the satellite into its 'nominal mission mode', and then move out of the Main Control Room into a Dedicated Control Room to start commissioning the radar payload," says Ian Shurmer.

Teams ready for launch

The mission control team comprises engineers dedicated to mission operations supported by experts from flight dynamics, ground stations, software systems and other specialist areas.

"It's really a 'team of teams', and by launch, we will have conducted 22 simulation training sessions," says Flight Director Pier Paolo Emanuelli.

"Most of those will have simulated reacting to unexpected contingencies, so the teams are definitely ready for launch."

The final dress rehearsal will be on 1 April, involving the teams in ESOC, Kourou and the ground stations in Sweden, Alaska, Norway and Antarctica.

"We've gotten to this point through a lot of hard work by the mission and payload teams and by our partners in industry and at Arianespace," says Pier Paolo. "We're looking forward to an excellent launch."

Explore further: Sentinel-1 unfolds its large solar wings and radar antenna

add to favorites email to friend print save as pdf

Related Stories

Swarm mission control ready for triple launch

Nov 20, 2013

After months of intensive training, the Swarm mission control team are ready for liftoff on Friday. The team will carefully shepherd the trio of magnetic explorers through their critical launch and early ...

Video: Sentinel-1A radar deployment

Jan 28, 2014

Testing the deployment of the Sentinel-1A radar antenna (in fast motion) in the cleanroom at Thales Alenia Space in Cannes, France. As the satellite is designed to operate in orbit, it is hung from a structure during tests ...

Weather satellite to be delivered in orbit to Eumetsat

Sep 10, 2012

Later this month, Europe's newest meteorology satellite, MetOp-B, will blast into space from Baikonur Cosmodrome. For mission control teams at ESA, liftoff marks the start of 72 hours of intense focus during ...

Mission control ready for Gaia launch

Dec 18, 2013

(Phys.org) —Shortly after a powerful Soyuz launcher lofts Gaia, ESA's new star mapper, into space on Thursday, teams on the ground will establish initial radio contact. Even then, tension will run high ...

Recommended for you

SDO captures images of two mid-level flares

10 hours ago

The sun emitted a mid-level flare on Dec. 18, 2014, at 4:58 p.m. EST. NASA's Solar Dynamics Observatory, which watches the sun constantly, captured an image of the event. Solar flares are powerful bursts ...

Why is Venus so horrible?

17 hours ago

Venus sucks. Seriously, it's the worst. The global temperature is as hot as an oven, the atmospheric pressure is 90 times Earth, and it rains sulfuric acid. Every part of the surface of Venus would kill you ...

Image: Christmas wrapping the Sentinel-3A antenna

20 hours ago

The moment a team of technicians, gowned like hospital surgeons, wraps the Sentinel-3A radar altimeter in multilayer insulation to protect it from the temperature extremes found in Earth orbit.

Video: Flying over Becquerel

20 hours ago

This latest release from the camera on ESA's Mars Express is a simulated flight over the Becquerel crater, showing large-scale deposits of sedimentary material.

Spinning up a dust devil on Mars

21 hours ago

Spinning up a dust devil in the thin air of Mars requires a stronger updraft than is needed to create a similar vortex on Earth, according to research at The University of Alabama in Huntsville (UAH).

User comments : 0

Please sign in to add a comment. Registration is free, and takes less than a minute. Read more

Click here to reset your password.
Sign in to get notified via email when new comments are made.