Audit: NASA doesn't have the money for big rockets

Jul 24, 2014

(AP)—NASA does not have enough money to get its new, $12 billion rocket system off the ground by the end of 2017 as planned, federal auditors say.

The Government Accountability Office issued a report Wednesday saying NASA's Space Launch System is at "high risk of missing" its planned December 2017 initial test flight. The post-space shuttle program would build the biggest rockets ever—larger than the Saturn V rockets which sent men to the moon—to send astronauts to asteroids and Mars.

"They can't meet the date with the money they have," report author Cristina Chaplain said. She said it wasn't because the space agency had technical problems with the congressionally-required program, but that NASA didn't get enough money to carry out the massive undertaking.

The GAO report put the current shortfall at $400 million, but did say NASA was "making solid progress" on the rocket program design.

NASA's launch system officials told the GAO that there was a 90 percent chance of not hitting the launch date at this time.

This usually means NASA has to delay its test launch date, get more money or be less ambitious about what it plans to do, said former NASA associate administrator Scott Pace, space policy director at George Washington University.

NASA is working on the problems GAO highlighted, but delaying launch or diverting from other programs would harm taxpayers, NASA Associate Administrator William Gerstenmaier wrote in the agency's response.

"Welcome to aerospace," Pace said, pointing out that large projects often end up as much as 50 percent over budget. He said that "is why you shouldn't believe initial cost estimates."

The has been reluctant to put an overall price tag on the Space Launch System. The GAO report says it will cost $12 billion to get to the first test launch and "potentially billions more to develop increasingly capable vehicles" that could be used for launches to asteroids and Mars.

Explore further: NASA begins engine test project for space launch system rocket

More information: GAO audit: www.gao.gov/assets/670/664969.pdf

Related Stories

GAO finds risks in NASA program

Apr 03, 2008

The U.S. Government Accountability Office says it's found major risks to the successful development of NASA's replacement for the space shuttle.

Recommended for you

New Horizons spacecraft experiences anomaly

7 hours ago

The New Horizons spacecraft experienced an anomaly the afternoon of July 4 that led to a loss of communication with Earth. Communication has since been reestablished and the spacecraft is healthy.

Dwarf planet Ceres offers big surprises for scientists

7 hours ago

The closer we get to Ceres, the more perplexing the dwarf planet grows. NASA's Dawn spacecraft has found several more bright spots as well as a pyramid-like peak jutting out of the frigid world's surface.

User comments : 0

Please sign in to add a comment. Registration is free, and takes less than a minute. Read more

Click here to reset your password.
Sign in to get notified via email when new comments are made.