MIT develops measures to predict performance of complex systems

Jan 19, 2007

Taking a cue from the financial world, MIT researchers along with experts in industry and government have developed a list of 13 measures that engineers can use to predict how well a system--or project--will perform before it is even finished.

Known as leading indicators, analogous measures are regularly used by economists, investors and businesses to help predict the economy's performance.

The idea behind the new set of leading indicators is to improve the management and performance of complex programs before they are delivered, in a more predictive way than simple business metrics.

"Leading indicators can provide important insights for managers of complex programs, such as those in the aerospace industry, and can allow them to make real-time adjustments to project activities, staffing and schedules to ensure a project stays on track," said Donna Rhodes, a principal researcher for MIT's Lean Aerospace Initiative (LAI).

The MIT leading indicators project, co-led by Rhodes and industry colleague Garry Roedler of Lockheed Martin, began in 2004 following an LAI/U.S. Air Force workshop on systems engineering that established the groundwork for the project. Systems engineering is an interdisciplinary approach to creating successful systems by focusing on variables including customer needs, system requirements, design synthesis and system validation, all while considering the complete problem.

A leading indicator may be an individual measure, or collection of measures, that are predictive of future system performance before the performance is realized.

Thirteen ways of looking at a system

The 13 leading indicators defined by the MIT team include risk handling trends. This indicator would be used by management to determine whether a project team is proactively handling potential problems (or risks) at the appropriate times with the goal of minimizing or eliminating their occurrence. If the actions to address a given project risk are not taken, then there is a higher probability that the risk will be realized, resulting in negative impact to project cost, schedule, performance or customer satisfaction. The insight gained through the use of this indicator can help identify where additional effort may be needed to avoid preventable problems or reduce impacts.

Several major aerospace companies worked to validate the 13 indicators in pilot programs during 2006, which helped refine them. Then, working in collaboration with the International Council on Systems Engineering (INCOSE), the leading professional society for systems engineering practitioners, the MIT team published a guidance document about the work. That document has been made available to the larger systems engineering community.

According to Rhodes, "The leading indicators project is an excellent example of how academic, government and industry experts can work together to perform collaborative research that has real impact on engineering practice."

The other leading indicators identified by the team are: system definition change; backlog trends; interface trends; requirements validation trends; requirements verification trends; work product approval trends; review action closure trends; risk exposure trends; technology maturity trends; technical measurement trends; systems engineering staffing & skills trends; and process compliance trends.

Source: MIT

Explore further: NTU and UNESCO to create mini-lab kits for youths in developing countries

add to favorites email to friend print save as pdf

Related Stories

New data about marsh harrier distribution in Europe

Oct 17, 2014

The use of ringing recoveries —a conventional method used to study bird migration— in combination with more modern techniques such as species distribution modelling and stable isotope analysis helps to ...

What do wildfires have to do with climate change?

Oct 14, 2014

As the western U.S. faces its third year of severe drought, firefighters are still battling two large fires in California. The state, which is experiencing its worst drought since record keeping began in ...

Recommended for you

Russia turns back clocks to permanent Winter Time

10 hours ago

Russia on Sunday is set to turn back its clocks to winter time permanently in a move backed by President Vladimir Putin, reversing a three-year experiment with non-stop summer time that proved highly unpopular.

Cloning whistle-blower: little change in S. Korea

Oct 24, 2014

The whistle-blower who exposed breakthrough cloning research as a devastating fake says South Korea is still dominated by the values that allowed science fraudster Hwang Woo-suk to become an almost untouchable ...

Color and texture matter most when it comes to tomatoes

Oct 21, 2014

A new study in the Journal of Food Science, published by the Institute of Food Technologists (IFT), evaluated consumers' choice in fresh tomato selection and revealed which characteristics make the red fruit most appealing.

User comments : 0