NYC flood defense plan advances, but completion years off

NYC flood defense plan advances, but completion years off
In this Oct. 30, 2012 file photo, water from New York Harbor spills into New York City's Battery Park during Superstorm Sandy. After ocean waters poured virtually unchecked into lower Manhattan during Sandy, experts began dreaming up a solution: a U-shaped barrier of earthen berms, walls and gates that would keep floods out and the nation's financial capital dry. Now, more than three years later, the idea has stacked up over $600 million in backing, including a $176 million shot in the arm from the federal government, but it is still hundreds of millions of dollars and several years away from becoming a reality. (AP Photo/Richard Drew, File)

After ocean waters poured into lower Manhattan during Superstorm Sandy, experts began dreaming up a solution: a U-shaped barrier of earthen berms, walls and gates that would keep floods out and the nation's financial capital dry.

Now, more than three years later, a version of that idea has stacked up over $600 million in backing, including $176 million from the federal government last week. But it is still hundreds of millions of dollars and several years away from being finished.

"We've been full steam ahead," said city resiliency director Daniel Zarrilli, "knowing that we don't really know how long we have before these things need to be in place."

Officials aim to start building next year and finish by 2022, building segments that can begin providing some protection before the more than 5-mile (8-kilometer) long project is complete. Still, there's no final plan yet for what it will look like, how much it will cost, or where the city will get the minimum of $300 million more it says is needed to finish. A devastating flood could come in decades or as soon as the next storm.

"There's much more hope" after the latest infusion of funding, said state Sen. Daniel Squadron, a Democrat who represents some affected areas. "But there's ongoing anxiety. Because this is not something that can be a generation-long project."

NYC flood defense plan advances, but completion years off
In this Oct. 29, 2012 file photo, flood waters from Superstorm Sandy surround a vehicle near the Consolidated Edison power plant in New York. With funds from different government sources, New York City plans a network of berms, floodwalls and a levee system to protect the city's southern tip from storm related flooding. (AP Photo/ John Minchillo, File)

Sandy struck in October 2012, killing over 180 people and causing $65 billion in damage in the U.S. alone. The storm swamped downtown Manhattan apartments and office buildings, flooded subways and cut power to nearly all of the lower half of the island.

Architects and engineers participating in a federal design competition later sketched out a 10-mile (16-kilometer) long "Big U" of barriers that varied by neighborhood.

The city's current proposals echo that idea but cover less territory, extending around Manhattan's southern end roughly from Bellevue Hospital on the East Side to half a mile (1 kilometer) north of the World Trade Center on the West Side. The path wraps around Wall Street and trendy neighborhoods, but also around several public housing developments by the East River.

NYC flood defense plan advances, but completion years off
In this Oct. 30, 2012 file photo, cars are submerged at the entrance to a parking garage in New York's Financial District in the aftermath of Superstorm Sandy. After ocean waters poured virtually unchecked into lower Manhattan during Sandy, experts began dreaming up a solution: a U-shaped barrier of earthen berms, walls and gates that would keep floods out and the nation's financial capital dry. Now, more than three years later, the idea has stacked up over $600 million in backing, including a $176 million shot in the arm from the federal government, but it is still hundreds of millions of dollars and several years away from becoming a reality. (AP Photo/Richard Drew, File)

Plans describe a mosaic of different approaches: a big, grassy berm in a park, floodwalls under an elevated highway, a levee system at Manhattan's southern tip, and in other spots moveable flood barriers, pumps and more. The proposal also calls for flood-proofing vulnerable and weaving plazas and park improvements into the water barriers.

Planning experts say it sets an example for multifaceted flood protection that "combines engineering with ecology with community" instead of just walling off water, says Rob Freudenberg of the Regional Plan Association, a research and advocacy organization.

Meanwhile, some institutions, utilities and building owners in low-lying lower Manhattan are doing their own storm-proofing. Transit officials have been working on seals for subway stations. And the city itself is working on other projects in Manhattan and elsewhere as part of a $20 billion plan to help New York weather storms and floods.

NYC flood defense plan advances, but completion years off
In this Wednesday, Oct. 31, 2012 file photo, Joseph Leader, Metropolitan Transportation Authority vice president and chief maintenance officer, shines a flashlight on standing water inside the South Ferry 1 train station in New York in the wake of Superstorm Sandy. The federal government promised $176 million that will enable New York City to start work on fortifying itself against flooding from future storms like Sandy. (AP Photo/Craig Ruttle, File)

Communities along the lower Manhattan waterfront are keenly waiting for the planned defenses.

"Obviously, we need a 'Big U,' not a 'Big J,'" says Tobi Bergman, chairman of a community board in the West Village, which saw some flooding in Sandy but is outside the protections planned so far. "(But) I think every New Yorker is glad to see progress begin."

  • NYC flood defense plan advances, but completion years off
    In this Jan. 19, 2016 photo, benches are fenced off in an area of the East Side Esplanade beneath the Manhattan Bridge in New York. Lower Manhattan, including the area in this photo, will receive an additional $176 million in federal funding for a large-scale flood protection system that will eventually wrap from Montgomery Street on the Lower East Side, around the tip of the borough, and up through Battery Park City. (AP Photo/Kathy Willens)
  • NYC flood defense plan advances, but completion years off
    In this Jan. 19, 2016 photo, a pedestrian walks along the East Side Esplanade in an area beneath the FDR drive just north of the Manhattan Bridge, left, in New York With $176 million promised by the federal government, New York City plans to construct a system of berms, floodwalls, moveable flood barriers, pumps and other infrastructure improvements to protect itself against floodwaters like those seen in Superstorm Sandy. (AP Photo/Kathy Willens)
  • NYC flood defense plan advances, but completion years off
    In this Jan. 19, 2016 photo, a jogger runs beneath the FDR Drive in an area below the Brooklyn Bridge in New York. Lower Manhattan will receive an additional $176 million in federal funding for a large-scale flood protection system that will eventually wrap from Montgomery Street on the Lower East Side, around the tip of the borough, and up through Battery Park City. The area in the photograph would be affected under the plan. (AP Photo/Kathy Willens)
  • NYC flood defense plan advances, but completion years off
    In this Jan. 19, 2016 photo, the Lower East side of Manhattan is seen in this view from Brooklyn Bridge Park in New York. Lower Manhattan will receive an additional $176 million in federal funding for a large-scale flood protection system that will eventually wrap from Montgomery Street in Chinatown around the tip of the borough, and up through Battery Park City. (AP Photo/Kathy Willens)

© 2016 The Associated Press. All rights reserved.

Citation: NYC flood defense plan advances, but completion years off (2016, January 27) retrieved 24 April 2024 from https://phys.org/news/2016-01-nyc-defense-advances-years.html
This document is subject to copyright. Apart from any fair dealing for the purpose of private study or research, no part may be reproduced without the written permission. The content is provided for information purposes only.

Explore further

Levees, removable walls in plan to protect NYC

7 shares

Feedback to editors