Japan PM orders Fukushima water leaks fixed

Sep 19, 2013 by Hiroshi Hiyama
Workers inspect the Fukushima Dai-ichi nuclear power plant on September 12, 2013, in a photo taken by Tokyo Electric Power Co (TEPCO). Japanese Prime Minister Shinzo Abe Thursday ordered the operator of the crippled Fukushima nuclear plant to work out a schedule for stemming radioactive water leaks as he toured the facility.

Japanese Prime Minister Shinzo Abe Thursday ordered the operator of the crippled Fukushima nuclear plant to work out a schedule for stemming radioactive water leaks as he toured the facility.

Tokyo Electric Power (TEPCO) had "to resolve the leaky water problem by setting a timeline", Abe told journalists travelling with him.

Abe said TEPCO chief Naomi Hirose told him the utility would secure by the end of fiscal 2014 (March 2015) another one trillion yen ($10 billion) in addition to the one trillion yen that it had already earmarked for urgently needed .

Abe was at Fukushima Daiichi power plant less than two weeks after he told the International Olympic Committee that the situation there was "under control".

The remark, delivered as part of Tokyo's successful bid to host the 2020 Summer Games, sparked criticism at home at a time TEPCO was palpably struggling to control the flow of mildly contaminated groundwater and was encountering problems with highly water making its way into the sea.

TEPCO has poured thousands of tonnes of water on the Fukushima reactors to tame meltdowns sparked by the March 2011 earthquake and tsunami.

The utility says the reactors are now stable but need to be kept cool to prevent them running out of control again.

Much of that now-contaminated water is being stored in temporary tanks at the plant and TEPCO has so far revealed no clear plan for it.

Abe stressed—as he did before Olympic chiefs—that the toxic water was contained within a small bay attached to the wrecked power plant.

"One of the main purposes of this visit was to see it for myself, after I made those remarks on how the has been handled," Abe said.

He said he would "work hard to counter rumours questioning the safety of the Fukushima plant".

Abe said he also urged TEPCO to demolish two reactors at the plant that escaped tsunami damage.

TEPCO officials said they would make their decision over Abe's suggestion by the end of the year.

Explore further: Shedding light on solar power

add to favorites email to friend print save as pdf

Related Stories

Steam seen at Fukushima reactors: TEPCO

Sep 13, 2013

Vapour has begun rising again from a reactor at the Fukushima nuclear power plant, more than two-and-a-half years after its core melted down, the site's Japanese operator said Friday.

Fukushima pipe leaking radioactive water: TEPCO

Sep 01, 2013

The operator of Japan's stricken Fukushima nuclear plant said Sunday it had found highly radioactive water dripping from a pipe used to connect two coolant tanks, patching it up using tape.

Japan to boost surveys off Fukushima: report

Sep 14, 2013

Japan's nuclear authority plans to conduct radiation contamination surveys at 600,000 points on the seabed off the crippled Fukushima nuclear plant, up from 200 places so far, a report said Saturday.

High radiation found in Fukushima groundwater

Sep 10, 2013

Japan pledged a renewed push to contain potentially hazardous leaks at Fukushima on Tuesday after the operator of the crippled plant reported spiking levels of radiation in groundwater.

Recommended for you

Audi to develop Tesla Model S all-electric rival

1 hour ago

The Tesla Model S has a rival. Audi is to develop all-electric family car. This is to be a family car that will offer an all-electric range of 280 miles (450 kilometers), according to Auto Express, which ...

A green data center with an autonomous power supply

7 hours ago

A new data center in the United States is generating electricity for its servers entirely from renewable sources, converting biogas from a sewage treatment plant into electricity and water. Siemens implemented ...

Can we create an energy efficient Internet?

8 hours ago

With the number of Internet connected devices rapidly increasing, researchers from Melbourne are starting a new research program to reduce energy consumption of such devices.

Shedding light on solar power

Nov 27, 2014

Everyone wants to save energy, but not everyone knows where to start. Grid Resources, a startup based out of the Centre for Urban Energy's iCUE incubator, is developing a new website that seeks to help homeowners ...

Energy transition project moves into its second phase

Nov 27, 2014

Siemens is studying new concepts for optimizing the cost-effectiveness and technical performance of energy systems with distributed and fluctuating electricity production. The associated IRENE research project ...

User comments : 0

Please sign in to add a comment. Registration is free, and takes less than a minute. Read more

Click here to reset your password.
Sign in to get notified via email when new comments are made.