NASA's Vehicle Assembly Building prepared for multiple rockets

Nov 09, 2012 by Bob Granath
A large space shuttle-era work platform is being lowered by crane for removal from high bay 3 of the Vehicle Assembly Building. In order for platforms to be safely lowered to the floor, the center of gravity had to precisely determine for each of the seven sections. The work is part of a center-wide modernization and refurbishment initiative to accommodate NASA’s Space Launch System and a variety of other spacecraft instead of the whole building supporting one design. Credit: NASA/Jim Grossmann

(Phys.org)—The Vehicle Assembly Building, or VAB, at NASA's Kennedy Space Center in Florida is undergoing renovations to accommodate future launch vehicles. A project of Ground Systems Development and Operations, or GSDO, space shuttle-era work platforms have been removed from the VAB's High Bay 3 and accommodations are being made to support a variety of future spacecraft, including NASA's Space Launch System (SLS) heavy-lift rocket. The changes are part of a centerwide modernization and refurbishment initiative in preparation for the next generation of human spaceflight.

One of the largest buildings in the world, the VAB was constructed in the mid-1960s to support stacking of the Apollo Saturn V rockets that took American astronauts to the moon. In the late 1970s, the facility was refurbished to accommodate the . Following three decades of flight, the space shuttle was retired in 2011.

Plans now call for the VAB to be able to support multiple types of space vehicles, including the SLS, Orion spacecraft and commercial rockets. NASA is partnering with private industry on rockets and spacecraft to take astronauts to low-Earth orbit and the . SLS will be an advanced heavy-lift providing a new capability for human exploration beyond Earth orbit.

"After more than 45 years of use, it was time to clear out and update the garage," said Jose Lopez, VAB senior project manager in the Vehicle Integration and Launch Support Branch of GSDO. "What makes this project such a major undertaking is the size."

The VAB is 526 feet tall, 716 feet long and 518 feet wide. It covers eight acres and encloses more than 129 million cubic feet of space. The building was constructed to withstand hurricanes and tropical storms with a foundation consisting of 30,000 cubic yards of concrete and 4,225 steel pilings driven 160 feet into bedrock.

As part of NASA's Ground Systems Development and Operations Program, a space shuttle-era work platform is being moved to the floor high bay 3 of the VAB. GSDO is developing the ground systems, infrastructure and operational approaches to safely process, the next generation of rockets and spacecraft. Credit: NASA/Jim Grossmann

The first step in the plan was to remove space shuttle-era work platforms, a project that presented numerous challenges.

"Imagine having to use a crane to safely lower to the ground a structure the size of a large home," Lopez said. "That provides perspective on what it was like to remove the old shuttle work platforms."

There were eight box-like support structures surrounding the shuttles during stacking in the VAB. One box platform structure had been removed in 2009 in preparation for the launch of the Ares I-X test vehicle in October 2009. Each platform structure had work stands, connections for electricity, water, pneumatics and other commodities.

"For this undertaking, we selected an experienced construction contractor to help us remove and demolish the work platforms," said Lopez.

Ivey's Construction Inc. of Merritt Island, Fla., began the task in early September. Working closely with NASA and other Kennedy contractors such as United Space Alliance and URS, as well as an on-call architectural and engineering firm BRPH, they helped ensure all systems in the VAB were disconnected from the platforms.

"There were several key factors to consider in order for platforms to be safely lowered to the floor, such as determining the center of gravity in each box platform section," Lopez said. He noted that a few of the platforms were the size of a three-story building and weighed between 300,000 and 325,000 pounds.

Several large space shuttle-era work platforms have been removed from the VAB and moved outside. Each platform will be demolished and the debris hauled away. Credit: NASA/Jim Grossmann

"The effort to lower each platform took place over several hours to ensure full control of the suspended load. They were then set on stanchions on the VAB floor," said Lopez. "Once checkout was complete, the platforms were moved outside on a transporter where Ivey's Construction crews demolished the structures so the debris could be safely hauled away."

The effort also required a great deal of coordination to ensure the project was completed safely.

"There are several renovation projects going on in the VAB right now," Lopez said. "Tour guests from the Kennedy visitor complex were coming through, so we made sure to coordinate the work so it could be completed with safety being our number one priority."

The next major project will be to install a new fire suppression system.

"This will modernize the fire suppression water supply system and bring it up to modern codes," he said.

Other major renovation includes code upgrades and safety improvements to the VAB. Some of the utilities and systems slated for replacement have been used since the VAB was completed in 1966. This initial work will be required to support any launch vehicle operated from Launch Complex 39 and will allow NASA to begin modernizing the facilities while vehicle specific requirements are being developed.

"Our plans for 2014 include awarding the constitution contract for the new access platforms, including related structures and systems required for the SLS," Lopez said.

Some of the current work has included removal of over 150 miles of obsolete Apollo- and shuttle-era cabling. This will make room for installation of more efficient, state-of-the-art command, communication, control and power systems needed to perform testing and verification prior to the SLS and other rockets being rolled out to the launch pad.

Explore further: Nasa begins development of Space Launch System flight software

add to favorites email to friend print save as pdf

Related Stories

NASA's space shuttle discovery rolls off launch pad tuesday

Dec 21, 2010

Space shuttle Discovery is scheduled to roll back from Launch Pad 39A to the Vehicle Assembly Building (VAB) at NASA's Kennedy Space Center in Florida for additional work related to its final scheduled mission. The first ...

All in Place for Space Shuttle Return To Flight

Jan 06, 2005

NASA marked a major milestone for the Space Shuttle's Return to Flight, as the redesigned External Tank rolled out today from the barge that carried it to the agency's Kennedy Space Center, Fla. The tank was taken to the ...

Image: Discovery and the Lunar Eclipse

Dec 21, 2010

Space shuttle Discovery waits to roll back from Launch Pad 39A to the Vehicle Assembly Building (VAB) at NASA's Kennedy Space Center in Florida in the early morning hours of Dec 21, 2010, with the beginning ...

Recommended for you

NASA head views progress on asteroid lasso mission

4 hours ago

Surrounded by engineers, NASA chief Charles Bolden inspected a prototype spacecraft engine that could power an audacious mission to lasso an asteroid and tow it closer to Earth for astronauts to explore.

Ecuador satellite collides with Russian space junk

4 hours ago

A small Ecuadoran satellite collided in orbit with the remains of a Russian rocket, but it is too soon to know how much damage it might have sustained, Quito's space agency said Thursday.

Forecast for Titan: Wild weather could be ahead

May 22, 2013

(Phys.org) —Saturn's moon Titan might be in for some wild weather as it heads into its spring and summer, if two new models are correct. Scientists think that as the seasons change in Titan's northern hemisphere, ...

SDO observes mid-level solar flare

May 22, 2013

UPDATE 16:30 p.m. EDT: The M7-class flare was also associated with a coronal mass ejection or CME, another solar phenomenon that can send billions of tons of particles into space. While this CME was not Ea ...

User comments : 0

More news stories

Hubble reveals the ring nebula's true shape

(Phys.org) —The Ring Nebula's distinctive shape makes it a popular illustration for astronomy books. But new observations by NASA's Hubble Space Telescope of the glowing gas shroud around an old, dying, ...

NASA head views progress on asteroid lasso mission

Surrounded by engineers, NASA chief Charles Bolden inspected a prototype spacecraft engine that could power an audacious mission to lasso an asteroid and tow it closer to Earth for astronauts to explore.

A hidden population of exotic neutron stars

(Phys.org) —Magnetars – the dense remains of dead stars that erupt sporadically with bursts of high-energy radiation - are some of the most extreme objects known in the Universe. A major campaign using ...

Controlling mood through the motions of mitochondria

(Medical Xpress)—Regulating the distribution of power in neurons is done by a system that makes the national electric grid look simple by comparison. Each neuron has several thousand mitochondria confined ...

Google Drive sports new view and scan enhancements

(Phys.org) —Google Drive has a new look and functions. The makeover in Google Drive features scanning and interface enhancements that put the user into "card" mode. The enhancements make it easy for the ...