New National Synchrotron Light Source II construction more than 70 percent complete

Apr 27, 2012 by Mona S. Rowe
An aerial view of the NSLS-II construction site

(Phys.org) -- Construction of the $912-million National Synchrotron Light Source II (NSLS-II) at the U.S. Department of Energy’s Brookhaven National Laboratory is more than 70 percent complete – on schedule and on budget. When operational in 2015, NSLS-II will enable unprecedented studies aimed at designing new materials for efficient energy generation and storage, building better catalysts, and engineering new kinds of electronics and medicines.

Today, Brookhaven Lab celebrated two major construction milestones — completion of the massive ring building and commissioning of the ’s linear accelerator.

“This is an exciting time for the project,” said Steve Dierker, NSLS-II Project Director and Associate Laboratory Director for Photon Sciences. “With the ring building complete, we are moving quickly to install the accelerator and start bringing in components for the experimental stations.”

Torcon, Inc., the general contractor for the ring building, began work in April 2009 under a $170-million contract, the single largest contract in the NSLS-II construction project. Torcon spent about 90 percent of its contract to hire subcontractors and suppliers on Long Island and in the region, bringing direct economic benefit to Long Island and New York State. Over the course of construction and operation, NSLS-II is expected to create more than 1,250 construction jobs, most from local labor unions, as well as 450 scientific, engineering and support jobs.

Construction of the ring building was done in five sections, the first completed in March 2011 and the final section in February 2012, when Brookhaven Lab took official occupancy of the building. The Laboratory has started installing equipment and components for the facility’s accelerator and experimental stations.

The NSLS-II accelerator will consist of three sections: a linear accelerator, or linac, where electrons are generated and accelerated to 200 million electron volts; a booster, which takes electrons from the linac and speeds them up to 3 billion electron volts; and a storage ring, where the electrons circulate to create synchrotron light in the form of x-rays. These x-rays are directed to experimental stations around the ring, where they will be used to probe the structure and function of everything from solar cells to cellular proteins.

Installation of the linac was completed in February and commissioning started at the end of March. During commissioning, workers will bring the linac to its designed operational parameters in a safe way.

On April 26, Brookhaven Lab suspended construction activities in the building for a “Celebration of Jobs Well Done” event. The Laboratory community took a first-time opportunity to walk all the way around the half-mile ring, following the clockwise path electrons will eventually take around the accelerator tunnel.

Groundbreaking for NSLS-II was in 2009. That same year, in large part because it was “shovel-ready,” the NSLS-II project received $150 million from the American Recovery and Reinvestment Act. That early infusion of dollars — not affecting the total project cost — enabled the Brookhaven National Laboratory to accelerate conventional construction.

NSLS-II will provide sophisticated new tools that will allow scientists to see materials at the scale of a nanometer, or one billionth of a meter — a capability not available at any other light source in the world. Working at the nanoscale, researchers will focus on some of the nation’s most important scientific challenges, including developing novel materials for clean and affordable energy production, molecular electronics, and high-temperature superconductors.

For more details about capabilities and future research projects at NSLS-II, go here.

Explore further: Controlling core switching in Pac-man disks

add to favorites email to friend print save as pdf

Related Stories

Brookhaven lab's new light source halfway there

Mar 22, 2011

(PhysOrg.com) -- The U.S. Department of Energy’s Brookhaven National Laboratory is now halfway toward completing construction of the National Synchrotron Light Source II (NSLS-II), a powerful x-ray microscope ...

NSLS-II Project Beamline Conceptual Designs

Nov 10, 2009

(PhysOrg.com) -- The NSLS-II Experimental Facilities Division achieved an important milestone in September when the conceptual design reports for the initial six project beamlines were completed and submitted to NSLS-II management.

ORNL's Spallation Neutron Source warms up for 2006

Sep 24, 2004

With the recent "warm commissioning" of its linear accelerator, Oak Ridge National Laboratory's Spallation Neutron Source (SNS) has passed a crucial test and milestone on its way to completion in 2006. The ...

Recommended for you

Controlling core switching in Pac-man disks

Dec 24, 2014

Magnetic vortices in thin films can encode information in the perpendicular magnetization pointing up or down relative to the vortex core. These binary states could be useful for non-volatile data storage ...

Atoms queue up for quantum computer networks

Dec 24, 2014

In order to develop future quantum computer networks, it is necessary to hold a known number of atoms and read them without them disappearing. To do this, researchers from the Niels Bohr Institute have developed ...

New video supports radiation dosimetry audits

Dec 23, 2014

The National Physical Laboratory (NPL), working with the National Radiotherapy Trials Quality Assurance Group, has produced a video guide to support physicists participating in radiation dosimetry audits.

Acoustic tweezers manipulate cell-to-cell contact

Dec 22, 2014

Sound waves can precisely position groups of cells for study without the danger of changing or damaging the cells, according to a team of Penn State researchers who are using surface acoustic waves to manipulate ...

User comments : 0

Please sign in to add a comment. Registration is free, and takes less than a minute. Read more

Click here to reset your password.
Sign in to get notified via email when new comments are made.